Duringplanningyousitdownandestimatethetimeneededforeachtaskandtotalthemtocomeupwiththeprojectestimate.Thisdurationiswhatyoucommittocompletetheproject.Whatiswrongwiththescenario?
A.The team did not create the estimate and estimating tales too long using that method B.The team did not create the estimate and a network diagram was not used C.The estimate is too long and should be created by management D.The project estimate should be the same as the customer's required completion date正确答案B