Which is the CORRECT approach for managing a large improvement initiative as smaller
Iterations?
A.Each iteration should be designed before starting the initiative and implemented without正确答案D
Feedback B.Feedback should only be taken into account when one iteration fails to meet its objective C.Feedback should be reduced for large improvements as it is unlikely that circumstances will
Change D.Each iteration should be continually re-evaluated based on feedback