The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance B.Schedule Variance
A.Earne B.Value C.Cost Performe D.Index正确答案A
The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance B.Schedule Variance
A.Earne B.Value C.Cost Performe D.Index正确答案A