()Assessesthepriorityofidentifiedrisksusingtheirprobabilityofoccurring,thecorrespondingimpactonprojectobjectivesiftherisksdooccur,aswellasotherfactorssuchasthetimeframeandrisktoleranceoftheprojectconstraintsofcost,schedule,scope,andquality.
欢迎免费使用小程序搜题/刷题/查看解析,提升学历,成考自考报名,论文代写、论文查重请加客服微信skr-web
()Assessesthepriorityofidentifiedrisksusingtheirprobabilityofoccurring,thecorrespondingimpactonprojectobjectivesiftherisksdooccur,aswellasotherfactorssuchasthetimeframeandrisktoleranceoftheprojectconstraintsofcost,schedule,scope,andquality.
A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan
正确答案B
×