Thecustomerasksyourprojecttobecompleted6monthsearlierthanplanned.Youthinkthistargetcanbereachedbyover-lappingprojectactivities.Thisapproachisknownas().
A.balance engineering B.fast-tracking C.leveling D.crashing正确答案B
Thecustomerasksyourprojecttobecompleted6monthsearlierthanplanned.Youthinkthistargetcanbereachedbyover-lappingprojectactivities.Thisapproachisknownas().
A.balance engineering B.fast-tracking C.leveling D.crashing正确答案B