()techniquesareusedtofindwaystobringprojectactivitiesthatarealignmentwiththeplanbyfasttrackingorcrashingtheschedulefortheremainingwork.
A.Schedule forecasts B.Schedule compression C.Change requests D.Data analysis正确答案B